The 3-week outlook for the Athens West Union Street Improvements project will be as follows: 

  • This week, the pipe crew will continue installing the 12-inch ductile iron pipe from the intersection of Jefferson and the fairgrounds entrance towards Shafer Street. Estimated installation time is 3 weeks, dependent on weather, underground utilities, and unknown issues that may be encountered. 
  • The second crew is working on service line tie-ins, with planned work from the Athens County Job and Family Services building moving towards Herrold Avenue at the end of the 3-week installation period.  

Access to local business entrances are open, with business open signs being installed.  

Traffic is one way (eastbound) from the SR 56/682 Intersection at West Union to the O’Bleness Hospital Entrance. Herrold Avenue is open to two-way traffic for the next two weeks. 

Motorists are advised to follow all posted signs and traffic patterns for public safety.

Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 740-593-7636.